Data Center Lease
| | | | | | | | | |

The State Froze Data Center Permits. Can the Developer Use That to Extend Its Deal on My Land?

You signed an option, a purchase contract, or a ground lease with a data center developer. Now the State of Texas has frozen data center permits, and a letter arrives saying the freeze is “force majeure,” the deadlines are suspended, and the developer needs more time. Before you agree, or ignore it, understand that the headline does not decide this. Your contract does.

On September 21, 2026, Governor Greg Abbott sent a letter to the executive director of the Texas Commission on Environmental Quality directing the agency to “halt all permits sought by data centers” and to “pause the issuance of all permits related to data center projects until ERCOT completes its review.” The letter also says that “no other state agency shall move forward with regulatory approvals related to data centers” until the state’s audits are done. You can read the Governor’s letter yourself. It is two pages long.

That came on top of the Governor’s August 3 letter pausing the Electric Reliability Council of Texas interconnection review for large data center loads, which I covered in Abbott’s Data Center Pause: What It Means for Texas Landowners. Projects that were already waiting on power are now also waiting on environmental permits, with no fixed end date.

Law firms that represent developers have already told their clients what to do: review force majeure and regulatory-delay clauses, and send notices. I have practiced Texas real estate and water law for more than 28 years, and I represent landowners, not developers. This guide is about the other side of that letter.

The Short Version

A state permit freeze does not automatically extend your contract. Under Texas law, whether delay excuses or extends performance depends on the words of the contract. A force majeure clause means what it says, and no more.

Force majeure usually suspends obligations, not deadlines on rights. Many clauses excuse a party that is “prevented or hindered from complying with” an obligation. A developer’s option to buy, or its right to terminate during a feasibility period, is a right with a deadline, not an obligation. Whether the clause reaches it depends on the exact language.

The developer has to connect the freeze to its delay. If no state permit application was pending, or the project was already stalled for other reasons, the freeze may not be what is delaying performance.

Option deadlines are strictly enforced in Texas. Texas courts have long treated time as of the essence in option contracts. An option not exercised on time and in the manner the contract requires generally lapses.

Your response can cost you rights. Accepting new payments, signing a “confirmation,” or saying nothing at the wrong time can be argued as agreement or waiver. Read the contract before you answer.

An extension is something you can sell. If the contract does not give the developer more time, the developer needs your agreement to get it. That has value.

Why Are Data Center Developers Asking Landowners for More Time?

Data center land deals are usually signed long before a project is certain. The developer ties up the land with an option, a purchase and sale agreement with a long feasibility period, or a ground lease with an option period, and then works on the things that make the project possible: power, water, zoning or platting, and state environmental permits for backup generation, on-site power plants, wastewater, and stormwater.

Those contracts have clocks. An option expires on a set date. A feasibility period ends, and the earnest money goes hard. A closing date arrives. A ground lease converts from option payments to full rent on a commencement date or an outside date.

The state actions of August and September 2026 put many of those clocks under pressure at once:

  • August 3: the Governor directed the Public Utility Commission of Texas and ERCOT to audit data centers and paused ERCOT’s review of large-load interconnections.
  • September 14: the Governor directed the Texas Water Development Board to enforce water use reporting against data centers. I explain what that means for neighbors in Will a Data Center Drain My Water Well?
  • September 21: the Governor directed TCEQ to halt data center permits until ERCOT completes its review, and required TCEQ to report on its compliance by October 19, 2026.

Local governments have added their own uncertainty. Cities are writing new data center rules, and some have adopted or considered moratoria, as I discuss in Can Texas Cities and Counties Ban Data Centers?

A developer facing a deadline it cannot meet has three choices: walk away, pay for more time, or claim the contract already gives it more time. The third choice is the cheapest for the developer, which is why the letters are going out.

Does Force Majeure Extend My Contract With a Data Center Developer?

Only if the clause, read as written, covers the event and the obligation the developer is trying to excuse. Texas does not have a general force majeure rule that applies to every contract. The term refers to whatever the parties wrote.

The contract controls

Texas courts read force majeure clauses as contract terms, not as equitable doctrines. As the Amarillo Court of Appeals put it in Sun Operating Ltd. Partnership v. Holt, 984 S.W.2d 277 (Tex. App.-Amarillo 1998, pet. denied), the scope and application of a force majeure clause is, for the most part, utterly dependent on the terms of the contract. Courts do not add events the parties left out, and they do not stretch a clause to cover obligations it does not mention.

Texas also does not imply a general duty of good faith and fair dealing into ordinary contracts. English v. Fischer, 660 S.W.2d 521 (Tex. 1983). That cuts both ways. A landowner cannot rely on “fairness” to hold a developer to a deadline the contract does not set, and a developer cannot rely on “fairness” to get time the contract does not give.

The questions that decide a force majeure claim

When a client brings me a force majeure notice, I work through the same questions:

  1. Is the event listed? Many developer forms list “governmental action,” “moratoria,” “delays in obtaining permits,” or “changes in law.” If the clause names the event, the developer’s argument is much stronger. If the clause lists only fire, flood, war, and similar events, the developer is relying on catch-all language.
  2. Does the clause cover this obligation? Force majeure clauses often exclude the obligation to pay money. Many cover only “obligations,” not rights, conditions, or deadlines to exercise an option.
  3. Did the event actually cause the delay? The clause typically applies only when the party is “prevented” or “hindered” by the event. That requires a real connection between the freeze and the specific performance at issue.
  4. Was it beyond the developer’s control? If the developer never applied for the permit, applied late, or filed an incomplete application, the delay may be of its own making.
  5. Did the developer give the required notice? Many clauses require written notice within a set number of days, with specified contents. A notice that is late, incomplete, or sent to the wrong address may not satisfy the contract.
  6. What is the remedy? Suspension for the duration of the event, an extension day for day, a right to terminate, or something else. Some clauses cap the total extension. Some give the other party a termination right if the event lasts too long.

Catch-all language and foreseeability

Many force majeure clauses end with a catch-all, such as “or any other cause beyond the reasonable control of the party.” Texas courts read that language narrowly.

In TEC Olmos, LLC v. ConocoPhillips Co., 555 S.W.3d 176 (Tex. App.-Houston [1st Dist.] 2018, pet. denied), the First Court of Appeals held that a party relying on a catch-all provision must show that the event was unforeseeable when the contract was signed. Specifically listed events do not carry that requirement, but a general catch-all does. Otherwise, the court reasoned, any event outside a party’s control would excuse performance and the clause would become meaningless. The court refused to read the catch-all to relieve a party of a risk it was aware of but did not address in the contract. The Supreme Court of Texas denied review.

That matters for timing. Governmental scrutiny of data centers in Texas was public long before September 2026. For a contract signed after the August 3 or September 21 letters, a developer relying on a catch-all will have a hard time arguing that a state pause was unforeseeable. For older contracts, the answer depends on when the contract was signed, what the clause lists, and what the parties knew.

Practice Insight

Do not assume foreseeability will save you. Most developer forms list governmental action or permitting delay by name, and for a listed event, foreseeability is generally not the test. The stronger landowner arguments are usually about scope (does the clause reach this deadline at all?), causation (did the freeze actually stop this project?), and notice (did the developer comply with the clause?).

If a developer has sent you a force majeure notice or asked for more time, do not answer until you have read what your contract says about delay. A reply written in a hurry can concede the very point in dispute.

Call 210-354-7600.

Representing Texas Land Owners. Not Data Center Developers.

Can a Data Center Developer Extend an Option Because of a Permit Freeze?

Not unless the option agreement allows it. An option gives the developer the right, but not the obligation, to buy or lease your land on stated terms by a stated date. Texas law is strict about how and when that right is exercised.

Texas courts have long held that time is of the essence in option contracts, and that an optionee must accept on the terms of the option. A purported exercise that changes the terms, or comes too late, is not an exercise. See Ducc Realty Co. v. Cox, 356 S.W.2d 807, 809 (Tex. Civ. App.-Waco 1962, no writ). If the option period ends without a proper exercise, the option generally lapses, and the developer’s rights end with it.

This is where the structure of the force majeure clause becomes critical. A clause that suspends a party’s “obligations” while it is prevented from performing them is a poor fit for an option, because the developer has no obligation to exercise. Exercising an option usually requires only written notice and, sometimes, a payment. A permit freeze does not prevent anyone from mailing a notice. What the developer really wants is more time to decide whether the project still works, and that is a business problem, not an impossibility.

Some option agreements expressly extend the option period for force majeure or for “regulatory delay.” Others give the developer paid extension rights, such as three extensions of six months each for a stated fee. If yours does, the question becomes whether the developer has followed the extension procedure exactly: timely notice, timely payment, and any other conditions.

Watch the recorded memorandum

Most data center options are recorded in the county real property records as a memorandum of option. If the option lapses but the memorandum stays of record, it can cloud your title and discourage other buyers. A well-drafted option requires the developer to sign a recordable release when the option ends. If yours does not, and the developer will not release, that becomes a title problem to address directly.

Approval Contingencies and Feasibility Periods

In practice, the clause that matters most is often not the force majeure clause at all. Data center purchase contracts and ground leases usually include a feasibility or due diligence period, and many include a separate approvals contingency tied to zoning, platting, utility service, power, water, or permits.

Those provisions typically answer the questions the developer is now asking:

  • How long the developer has to obtain approvals, and whether it can extend that period, for how long, and at what price.
  • Whether extension payments are refundable and whether they apply to the purchase price.
  • What happens if approvals are not obtained by the deadline: termination with a refund, termination without a refund, or an automatic extension.
  • Whether the developer must diligently pursue the approvals, and what proof of that it must provide.
  • Whether a governmental moratorium is treated specially, for example by tolling the approvals period.

If the contract already addresses governmental delay in the approvals contingency, the developer may not need force majeure at all, and the landowner’s rights will be defined by that section. If the approvals contingency sets a deadline and says nothing about moratoria, a developer that invokes general force majeure language to extend it is asking for more than the specific section gave it. Texas courts generally give specific provisions effect over general ones when the two conflict.

For a broader view of these provisions, see A Texas Landowner’s Guide to Selling Property for a Data Center and Leasing Your Land to a Data Center in Texas.

Does the Permit Freeze Make Performance “Impossible”?

Rarely, as to a landowner’s contract. Even without a force majeure clause, Texas recognizes that a governmental order can discharge a party’s duty to perform in limited circumstances. In Centex Corp. v. Dalton, 840 S.W.2d 952 (Tex. 1992), the Supreme Court of Texas held that a party was excused from paying a fee after a federal banking regulator issued an order that made the payment illegal. The governmental order did not merely delay the performance. It prohibited it.

A developer facing the permit freeze is in a different position. The freeze, by its own terms, pauses the issuance of permits “until ERCOT completes its review.” It does not prohibit anyone from buying land, paying an option fee, closing a purchase, or paying rent. A developer may argue that the project no longer makes economic sense on the original timeline, but a deal becoming less attractive is not the same thing as performance becoming impossible.

The legal footing of the freeze itself is also contested. The letter cites no statute, and the air permit statute, Health and Safety Code Section 382.0518, says the commission “shall grant within a reasonable time” a permit that meets the statutory standards. Whether the freeze will last, be narrowed, or be challenged is uncertain. That uncertainty is one more reason for a landowner not to agree to an open-ended extension tied to it.

How Should a Texas Landowner Respond to a Force Majeure or Extension Letter?

Carefully, in writing, and only after reading the contract. The first response often shapes everything that follows.

Your first steps

  1. Calendar every date. The date the letter was received, the current deadline the developer wants to move, any notice deadlines in the force majeure clause, and any deadline for you to object.
  2. Pull the whole contract, including every amendment, extension letter, and the recorded memorandum. Read the force majeure clause, the approvals contingency, the extension provisions, the notice clause, and any nonwaiver clause together.
  3. Check the notice itself. Was it sent by the method the contract requires, to the right address, within the required time, with the required information?
  4. Ask for specifics. Which permit? From which agency? When was the application filed? What is its status? How does the freeze delay the specific deadline at issue? TCEQ permit applications are public records, so many of those answers can be checked. I explain how to find state and district records about a project in How Much Water Is the Data Center Next Door Using?
  5. Do not accept anything that changes the deal informally. That includes new payments under different terms, revised closing statements, or a “confirmation” that the deadline is extended.
  6. Reserve your rights. If you dispute the claim, say so in writing, and say that you reserve all rights under the contract.

Silence and waiver

Waiver under Texas law is the intentional relinquishment of a known right, or conduct inconsistent with claiming it. A landowner who accepts late option payments, lets work continue on the land after a deadline, or writes an email saying “take whatever time you need” may face an argument that the deadline was waived or extended.

A nonwaiver clause helps. In Shields Ltd. Partnership v. Bradberry, 526 S.W.3d 471 (Tex. 2017), the Supreme Court of Texas held that nonwaiver provisions are binding and enforceable, and that engaging in the very conduct a nonwaiver clause says is not a waiver is insufficient, as a matter of law, to nullify the clause. The Court also recognized that a nonwaiver clause can itself be waived by conduct that is unequivocally inconsistent with it. Do not test that line by accident.

Practice Insight

The most common mistake I see is a friendly reply. The developer’s land agent calls, explains the freeze, and asks if the landowner is “okay with a little more time.” The landowner says yes, and the agent sends an email confirming the conversation. Six months later, that email is Exhibit A. Be courteous, but do not agree to anything until you know what you are giving up.

If the Developer Asks for an Extension, What Can I Ask for in Return?

If the contract does not give the developer the time it needs, the developer needs your agreement. That puts you in a position to negotiate. Common terms for an extension include:

  • A non-refundable extension payment that does not apply to the purchase price, paid directly to you, not into escrow.
  • Release of existing earnest money to you, so it is no longer refundable.
  • A price increase, or a reappraisal, to reflect the longer hold.
  • A hard outside date by which the developer must close, commence the lease, or release the land, regardless of any further governmental delay.
  • A cap on total extensions, so one extension does not become an indefinite hold.
  • A recordable release signed now and held in escrow, to be recorded if the developer does not close by the outside date.
  • Payment of carrying costs, such as property taxes and any rollback tax exposure during the extension.
  • Restoration of any testing, clearing, or survey work if the deal does not close.

Any extension should be in a written amendment signed by both parties, and it should say expressly that it resolves the force majeure claim. An extension that leaves the developer free to claim more time under force majeure later has not bought you certainty.

An extension request is a negotiation, not a formality. Before you agree to hold your land off the market for another year, know what your contract already gives the developer, and what it does not.

Call 210-354-7600.

Representing Texas Land Owners. Not Data Center Developers.

If You Have Not Signed Yet: Clauses to Insist On

If you are negotiating with a data center developer now, the freeze is a known risk. Allocate it in the contract rather than leaving it to a force majeure argument later. At a minimum:

Issue What a landowner-protective contract says
Governmental moratoria Addressed expressly, in one place. Either the developer bears the risk, or any extension is limited, paid, and capped.
Force majeure scope Applies to both parties, excludes payment obligations, does not extend the option period or approvals deadlines unless stated, and requires prompt written notice with specifics.
Outside date A final date for closing or lease commencement that no event extends.
Extension payments Non-refundable, paid to the landowner, not applicable to the price.
Diligence The developer must apply for named approvals by set dates and report status on request.
Termination If the developer terminates, it releases the memorandum, restores the land, and delivers reports and surveys.
Nonwaiver Accepting payments or allowing access after a deadline does not waive or extend it.

Every one of these terms is easier to obtain before you sign than after the developer has the land tied up. If a letter of intent is in front of you, the time to address the freeze is now. My guide to selling property for a data center covers the rest of the contract, and my guide to data center ground leases covers rent commencement and outside dates in a lease.

What About the Land Next Door?

If you did not sign anything, but your neighbor did, the freeze may slow the project but does not necessarily stop it. Local approvals, groundwater district permits, land acquisition, and site work may continue. If you are trying to understand your options before construction begins, start with Can I Stop a Data Center Next to My Texas Property? and Living Next to a Data Center: A Texas Landowner’s Guide.

If you are under contract with a data center developer, the permit freeze is the moment to read your contract, not the moment to assume the deadlines are gone. Find out which clause controls before you respond.

Call 210-354-7600 to talk through your contract by video or in person.

Representing Texas Land Owners. Not Data Center Developers.

Related Guides

Frequently Asked Questions

Does Governor Abbott’s data center permit freeze extend my contract with a data center developer?

Not automatically. The Governor’s September 21, 2026 letter directs TCEQ to pause the issuance of permits related to data center projects. It does not amend private contracts. Whether a developer gets more time depends on the contract’s force majeure clause, approvals contingency, and extension provisions, read as written.

Is a government permit freeze force majeure under Texas law?

Only if the contract’s force majeure clause covers it. Texas courts treat force majeure as a matter of contract language. If the clause lists governmental action, moratoria, or permitting delays, the developer’s argument is stronger. If the developer relies on a general catch-all, Texas courts have required the event to have been unforeseeable when the contract was signed, as in TEC Olmos, LLC v. ConocoPhillips Co. The developer must also show that the event actually prevented or delayed the specific performance at issue.

Can a data center developer extend an option to buy my land because of the permit freeze?

Only if the option agreement provides for it. Texas courts treat time as of the essence in option contracts, and an option not exercised on time and on its terms generally lapses. Many force majeure clauses suspend obligations, while an option is a right, so whether the clause extends the option period depends on its exact wording.

Should I accept an extension payment from the developer?

Not until you know what it means. Accepting a payment on new terms, or one the contract does not call for, may be argued as agreement to an extension or a waiver of a deadline. If you agree to an extension, put it in a written amendment signed by both parties that states the payment, whether it is refundable, the new deadline, and an outside date.

What happens if I ignore a force majeure notice from a data center developer?

Ignoring it can be risky. Some contracts treat silence as acceptance, or set short deadlines for objections, and silence combined with accepting payments or allowing continued access to your land can support a waiver argument. A short written response disputing the claim and reserving your rights is usually better than no response.

Does the permit freeze make it impossible for the developer to close?

Usually not. Texas recognizes that a governmental order can excuse performance when it makes the performance illegal, as in Centex Corp. v. Dalton. The permit freeze pauses permit issuance. It does not prohibit buying land, paying an option fee, closing, or paying rent. A deal becoming less attractive is not the same as performance becoming impossible.

I have not signed yet. How do I protect myself from future permit freezes?

Address governmental delay expressly. A landowner-protective contract states whether moratoria extend any deadline, limits and prices any extension, sets a hard outside date, makes extension payments non-refundable, requires the developer to apply for approvals by set dates, and requires a recordable release if the deal ends.

About the author. Trey Wilson is a San Antonio real estate and water lawyer with more than 28 years of experience representing Texas landowners in land sales, options, ground leases, easements, groundwater and surface water matters, nuisance and flooding claims, and real estate litigation. He represents Texas landowners affected by data center development. He does not represent data center developers.

Representing Texas Land Owners. Not Data Center Developers. To discuss a data center contract, call 210-354-7600.

This article is general information about Texas law and is not legal advice. It does not create an attorney-client relationship. Contract terms vary widely, outcomes depend on specific facts, and the state actions described here were ongoing as of publication.